Q framed by me from PMBOK

A project management team calls bids for procuring some customized products and for that they have to mention procurement statement of work in their request. From where they will able to develop the required procurement Statement of Work:
1. Project Charter
2. Project Scope baseline
3. Project scope statement
4. Project WBS

Answer is 4.

This is all about jasa seo terpercaya

**deleted duplicate comment**

hint - read conduct procurement

Correct answer is
2. Project Scope baseline.

project scope statement..


answer is 3)

Next Q

In network diagramming like critical path in CPM, A critical chain in critical chain method may be defined as a
1. Shortest project activities chain
2. Longest project finish date
3. Resource constrained critical path
4. Path having Free Buffer among the activities

Good Morning Respected Pawarji Sir aka RPS,


 


The answers are:


 


1. The answer is Scope Baseline and it is on page 356 of PMBOK. PSoW is an output of Plan Procurements.


 


2. "C". Critical Chain talks about resource constraints on a CPM.


 


Please let us know of the answers.


 


Warmly, KK...

Yes you are right . PMBOK p 155 (186pdf) last para ist line.

Q. Which one of the following is correct asending order of severity of causes of conflict which may affect the progress, at project work:



  1. Resources, ---- >    Personalities, -----> Schedules

  2. Priorities, ------     > Resources,------ >   Schedules

  3. Resources, -------> Preorities,---------->  Schedules

  4. Personalities,----  > Resources,------- >  Schedules

Regards

Ans 2. Priorities -> Resources -> schedules 

What is source (base ) of your answer?

How should I agree upon?

Pawar....i just based the answer from my gut experience...

 - Priorities like Org priority mostly on budget or perks for one proj than another, which in my opinion are manageable 

- Rescources can yield a lot of trouble, both Human and non-human...they are the raw materials for production and alike and a small conflict can trigger bigger issues. scarce resources , infra structure , a particular technology engineer etc

- Schedules , these directly meddle with the customers/stakeholders interest and can easily upset them (due to a delayed delivery) ,the impact is comparitively huge and potentially devastating, sometime could even cost the project and any future opportunities that shoyuld be in pipeline... 

 

Answer pls...

Actually it is not from PMBOK.


PMBOK just speaks - 4 sources of CONFLICTS among project team



  1. Scarce Resources (9.4.2.3)

  2. Schedules - pl pay attention - schedule is here staff assignment schedule (resource calanders)also. dont miss this point.(9.2.3.2)

  3. Scheduling Priorities(9.4.2.3)

  4. Personal way of working (style of working) - Personallities(9.4.2.3)

Like PMBOK does not suggest, sequencing 6 ways of resolving conflicts, only says these are situationally important,  But few writers arrange them in a order. Says Confronting is most up in order where withdrawing is last one , some says Forcing is last(this not correct- by many of good writers).


Referencing above question, I read in RITA and one question similar (not ditto- even you can't catch it - from human resource chapter last pages series.)


On that basis I prepare it and tuned it by a side source of  HAROLD KERZNER (read  my post in this forum "easy six").


and my answer is 3.


                                             - Schedules 1    ^


                     - Priorities 2                              ^


- Resources 3                                                 ^


http://er-sspawar.blogspot.in/2012/08/from-v-k-verma-rank-of-conflicts.html


or http://er-sspawar.blogspot.in

Q


A team member is giving a presentation with a slide show after a Speech session in a forum, he is using which type of communication from these four:



  1. Formal Verbal

  2. Informal Verbal

  3. Formal Written

  4. Informal written

 

1) Formal Verbal

yes it is


formal verbal - created form RITA

Risk Register contains, most possible correct one is



  1. Name of risk owner, old  and current risk and response record, risk rating, watch list

  2. Identified risk and risk response of current projects, risk symptoms, probability & impact,

  3. Risk and Risk analysis, tools and techniques, risk scenarios

  4. Risk and hazards, risk identifier and owner, risk response

Ans: 2

Hi RPS,


 


The answers are A and B for 3 and 4 respectively.


 


Warmly, KK...

yes Q4 ans is no 2 more correct, one is old project risk response is wrongly added.


RISK REGISTERS seems a big document and requires continue updating, this q can be verified directly from PMBOK.

Q


Procurement Management Plan is a part of Project Managemant Plan, but it is formalised as:



  1. Formal document

  2. Informal document

  3. Highly detailed or broadly framed document

  4. All above

 

Q


Procurement statement of work should be concise clear and complete. Sometimes it describes Collateral Services if required, here “Collateral Services” means:


A.    A term of team agreement contract, defines the responsibility of each participant


B.    Common issues of buyer and seller in a contract


C.    Performance report or post-project operational support


D.    Side by Side activities of buyer and seller


 

Q no 5 Q no 6 both are ctly direbased on PMBOK 4E- PPM KA.

Hope this hint will be sufficient.

I give a 5 rating to these questions from my side.

Q5 -Ans:4


Q6- Ans:C

Q


Procurement statement of work should be concise clear and complete. Sometimes it describes Collateral Services if required, here “Collateral Services” means Performance report or Post-project operational support, Here Performance Report means:



  1. Procurement Audit report

  2. Out put of Report Performance Process

  3. Services and performance followup during any agreed period

  4. None of the above

  Out put of Report Performance Process

Answer is 3- Services and performance follow up for a warranty period.

Q-8

Budget Amount of Management reserve should atleast be known to :

  1. Project Manager
  2. Senior Management /project Sponsor
  3. Project Manager and Senior Management /project Sponsor
  4. Project Team and Sponsor or Equivelant

 

 Budget Amount of Management reserve should atleast be known to : Project Manager

Management reserve is owned by Senior management/Project Sponsor - it is only known to him out of all above options. PMBOK P177/7.2.2.2

Management Reserve is included to:

  1. Cost baseline
  2. Project Budget
  3. Total Budget
  4. Authorized Budget

  Management Reserve is included to:  Project Budget

Answer is Total budget

PMBOK E4 P174/7.2 and P177/7.2.2.2

Which one is not a Projects Log:

  1. Action Item Log
  2. Assumptions Log
  3. Time Log
  4. Change Request Log

Q-11

Verbally communicated change request should be

A.     Recorded  in some cases in configuration management system

B.     Recorded in some cases in change  management system

C.    Avoided and not to be entertained

D.    Option A and B

Q-12

In a Teaming agreement, when the buyer and seller collectively perform, they are:

A.     Jointly as a Seller

B.     Jointly as a Buyer

C.    Both A and B

D.    In a In-house Project

Q-10: 3,


Q-11: D,
Q-12:C


Answers Please!!!!

Ans of 10 and 11 are correct.


Change request PMBOK P94 ist para


Time log is not a PMBOK term


Last One is  B - Buyers only


They will share the profit - being a Buyer in Business market, Buyer can perform partly inhouse , partly can sublet.


Seller or pure inhouse project do not have all possibility as buyer.

Q13


Project Integration Management entails:


A.     Making choices among resource allocation


B.     Making trade-offs among competing objectives and alternatives


C.    Managing the interdependencies among the project management knowledge areas


D.    All above


 

Thanks.


For Q:13Ans: D

Yes Ch 4 Ist PARA

Q14
Resource Calendars specify when and how project resources will be available throughout the project period. Here Resources means
A. Manpower, and Machineries
B. People Material and Equipment
C. Skilled and unskilled workforce and Staff
D. Men Machine Money and Material

Q15
Resource Calendars are input to almost 5 different processes have output source process/es:
A. Acquire Project Team and Conduct Procurements
B. Acquire Project Team
C. Staffing management Plan and Create WBS
D. Staffing management Plan

Cross –Training is
1. Term of staffing management to train trainees changing the team groups alternatively
2. It’s a sharing and interchanging of knowledge and expertise among team members from different parts of world working at a project.
3. Its cross country training while working at new place across the world
4. It is cultural exchange while working abroad.

------

Team language is
1. A code language while project team at secret mission.
2. Few specific terminology developed by Project manager to follow team for fast working and time saving
3. A different language or norm than their native one among project team working on a global project.
4. A bunch of slang words developed among certain project team.

--------------

Which Document will identify People who are on the project team?
1. Staffing management plan
2. Resource calendar
3. Project staff assignment
4. Responsibility assignment matrics

2,3,3

You as a project manager have completed a project successfully and now you are preparing a list for reward and recognition for your project team members. Being a PMP certified PM, you have missed something:


1.     Zero Sum award system is not analysed


2.     Forget to refer list of top performers


3.     Award and recognition were be given during project and not after the project completion


4.     All above


 

 3

A project manager was engaged with his/her team members’ issues, he was listening issues at transparent ground from all equally and examining alternatives,

and after end of resolution a give and take attitude was observed, which type of conflict technique that project manager was performing:

A.     Problem solving

B.     Collaborating

C.     Accommodating

D.     Compromising

 compromising