Q framed by me from PMBOK
Submitted by sspawar on Sun, 08/19/2012 - 06:26
A project management team calls bids for procuring some customized products and for that they have to mention procurement statement of work in their request. From where they will able to develop the required procurement Statement of Work:
1. Project Charter
2. Project Scope baseline
3. Project scope statement
4. Project WBS
Forums:


sspawar
Wed, 10/17/2012 - 15:54
Permalink
STATUS REPORT AND PROGRESS REPORT
STATUS REPORT AND PROGRESS REPORT
sspawar
Sat, 10/20/2012 - 00:34
Permalink
STATUS REPORT AND PROGRESS REPORT
if I say
at what page you are today reading pmbok
and your answer if would be = page 330
it is a status of your study. or status report
if I ask how many pages you have read in last week
and your answer would be if == 15 pages
it is progress of your study or progress report
hence option C will be the answer.
sspawar
Wed, 10/17/2012 - 16:17
Permalink
change request and WPI
Work performance information is an output of direct and manages project execution, it is used as input to following process except:
A. Monitor and control project work
B. Perform integrated change control
C. Report performance
D. Administer procurement
Q
Approved change request may includes following except
A. Corrective action
B. Preventive action
C. Policies modifications
D. Resource reassessment
sspawar
Wed, 10/17/2012 - 17:03
Permalink
Project life cycle
All projects can be mapped to the following life cycle structures:
A. Starting the project, Organizing and Preparing , Carry out the Project work and Closing the project
B. Feasibility stage, Initiation of project, Execution and Control, and Close out
C. Initiating , Planning, Executing, Monitoring and Controlling , and Closing
D. Concept, Design, Planning and Implementing, and Delivering
sspawar
Thu, 10/18/2012 - 12:27
Permalink
close project
Q1
During project closure to ensure all project requirements have been completed, as a project manager you will perform all below except one:
A. Review prior phase closure documentation
B. Review customer acceptance documentation from verify scope process
C. Review Contracts
D. Review of success and failure process
Q2
Lesson learned will include information on all below except:
A. Issues during projects
B. Techniques that found significant
C. Risks
D. Requirements
ssundar
Thu, 10/18/2012 - 14:29
Permalink
Hope, below may be the
Hope, below may be the answers..
Q1 (A) .. Nothing to do with prior phase closure documentaion during current phase.
Q2 (D) .. Lessons learned is more about how efficiently handled on issues and risks. So, Requirement is excluded.
sspawar
Fri, 10/19/2012 - 23:25
Permalink
Sorry Sunder I could see it
Sorry Sunder I could see it very late ,
2nd question is rightly answered no doubt LL mainly stress over Risk, issues, and technical significance as per PMBOK
Ist question is little tricky --- all 4 is required to document before closure , PMBOK p 102., also second line of 4.6.
But in D- option is shown as "Review of success/failure process", -- processes never be reviewed anywhere except in quality - process improvement. while closure - success/failure audited.
Collect ------records -----files
Audit ------- success/failure ----
Archive ------ information
Gather ----- LL
sspawar
Sat, 10/20/2012 - 01:19
Permalink
DIFINE SCOPE
In define scope process project documents are updated which includes all except:
A. Stakeholder register
B. Requirement documentations
C. Requirement traceability matrix
D. Risk register
sspawar
Sat, 10/20/2012 - 23:48
Permalink
What is non- work schedule activity?
What is non- work schedule activity?
A. It is effort hours available in Resource calendar which are not be utilized during a schedule.
B. It is buffer available in Critical Chain method
C. It is a type of activity, which runs parallel to the main activities, and not measured separately.
D. These are activities required efforts but no separate schedule.
sspawar
Sun, 10/21/2012 - 00:38
Permalink
Resource allocation
While reviewing a schedule network and resource allocation of a sub-project, a senior manager, objects that in certain activities resources are over-allocated. Here Over allocation means:
A. One resource is allocated over 2 or more activities in same time.
B. More resources than required are allocated at certain activities in same time.
C. Few resources are idle in certain activities
D. All above
sspawar
Sun, 10/21/2012 - 06:00
Permalink
Schedule Data
Schedule data for project schedule includes:
A. Mile stones, Schedule Activities, activity attributes, Activity related Assumptions and Constraints
B. Cash flow program, delivery and order schedules
C. Resource Histograms
D. All above
sspawar
Fri, 05/03/2013 - 09:30
Permalink
Is it tough question?
A project having BAC = 20000, in a point of time when its 80% work was over, its TCPI is reported as 1.2. What is its CPI?
A.
0.833
B.
1.20
C.
0.96
D.
0.90
san
Fri, 05/03/2013 - 11:47
Permalink
Ans :C. 0.96
Ans :C. 0.96
sspawar
Fri, 05/03/2013 - 23:14
Permalink
San you are absolutely
San you are absolutely correct !!!!!!!!!!!!!!
how you score this question? easy/moderate/tough
san
Sat, 05/04/2013 - 05:29
Permalink
Pawar Sir,This question is
Pawar Sir,
This question is completely based on the formulas. If we know the formulas, we can execute this question correctly. I will rate this as Moderate.
Thanks
sspawar
Fri, 05/03/2013 - 16:16
Permalink
EVM Question
You are following EVM methodology for forecasting project estimates, in this prospects which statement is true?
crushPMP
Sat, 05/04/2013 - 01:33
Permalink
^ I'll go with 4 on this
^ I'll go with 4 on this one. All sentences are correct
sspawar - good questions, keep them coming.
sspawar
Sat, 05/04/2013 - 03:51
Permalink
CrushPMP Re-think
CrushPMP Re-think
san
Sat, 05/04/2013 - 05:22
Permalink
This could be 2.
This could be 2.
sspawar
Sat, 05/04/2013 - 05:30
Permalink
It is an open fundamental,
It is an open fundamental, but rarely we reach to that.
to make aware of that fact, I made this quest.
Still not the right one.(as per my view)
san
Sat, 05/04/2013 - 05:43
Permalink
I had a doubt between 1 and
I had a doubt between 1 and 2.
Now , I go with option 1.
Please provide the explanation as to validate my analysis.
Thanks
sspawar
Sat, 05/04/2013 - 07:13
Permalink
What does this formula
What does this formula say?
TCPI = (BAC - EV) / (BAC - AC)
take example of just above one question
BAC = 20000, TCPI = 1.2
Planned ETC at 80% completion, should be 4000, but it is in fact 3333.33, and with the same BAC, project is getting completed. -- hence option 1 is not true.
It is an atypical case , because CPI is not same through out the project - but with the same BAC, project is getting completed. -- hence option 2 is not true.
What is problem with option 3 - in typical case , through the project period only one CPI remains all the time.
Hence option 4 is not true.
san
Sat, 05/04/2013 - 07:51
Permalink
Yes, in typical case
Yes, in typical case CPI remains same. But how can TCPI and CPI could be the same. Please clarify this point.
Thanks
sspawar
Sat, 05/04/2013 - 09:47
Permalink
TCPI by definition is
TCPI by definition is nothing but CPI of remaing work with available fund.
vmetha
Thu, 06/27/2013 - 14:50
Permalink
Thanks,
This kind questions exactly what i was looking for...Thanks again..
jobros
Sun, 11/24/2019 - 23:19
Permalink
Great Job Dude
That's a great job dude. Ayo pakai jasa seo tahunan dari kita.
Pages