Q framed by me from PMBOK

A project management team calls bids for procuring some customized products and for that they have to mention procurement statement of work in their request. From where they will able to develop the required procurement Statement of Work:
1. Project Charter
2. Project Scope baseline
3. Project scope statement
4. Project WBS

Q.
Unspoken and often unwritten set of informal

rules that govern individual behaviors in a

group are called "Group Norms". Without group norms,

individuals would have no understanding of how to act in social situations.

How this "Group Norms" are helpful in a project management:

1.     Reduce the amount of conflict among that group.
2.     It is a cultural diversity and people concerned will act friendly together
3.     Solve the unforeseen issues among group members
4.     It maintains social activity while members are at Company Social Responsibility (CSR)

 NOt sure, just a guess, answer is 3.

Question: 22
As the project activities are being performed, the majority of effort in Time Management Knowledge Area will occur in the ------- process to ensure completion of project work in a timely manner.
A. Define activities 
B. Schedule activities
C. Control schedule
D. Estimate activities durations

 C

Risk if occurs it can affect at least one objective of a Project, that objectives are:

A.    Cost, Quality, Time and Scope

B.    Cost, Scope and Time

C.    Cost, Scope, Time, Quality and Procurements

D.    Cost, Scope, Time,  Quality and Communication

Causes of happening a risk is not

A.    Requirements

B.    Constraints and Assumptions

C.    Priorities

D.    Conditions

Risks are uncertain events in Projects, which statement is true regarding

A.    Risk exists the moment Project is conceived

B.    Risk can exist only when risk is identified

C.    Risk response is a process that can avoid any risk

D.    Throughout the life cycle risks are certain

Based on my knowledge, answers are:  A, A, A.

Q

 Stakeholder register includes information about all below except one

  1. Stakeholder Groups
  2. Stakeholder Identification
  3. Stakeholder assessment
  4. Stakeholder classification

 1.

One way of classification of Stakeholders, is Internal/ External, like they may also classify as:

A.    Supporter/ Neutral/ Resistor

B.    Negative / Neutral/ Integrative

C.    Supportive/ Idle/ Negative

D.    Positive / Dual/ Negative

based on my knowledge, guessing answer is A. Please confirm.

In sequence of your reply true answer are:   2 c a c a 1 a

                                   against 3 c a a a 1 a =5/7  =72%

Ist question is from conduct procurement

Rest of questions are also from related topics/sections

Thanks



To whom, what, when, how and by whom information will be dealt is a subject matter of

  1. Distribute information process
  2. Plan communication process
  3. Manage stakeholder expectations process
  4. Project manager

 2.

yaa it is 2

In a project most of the expenses incurred in executing process group, like Most of the expenses in a project incurred in which head:

  1. Organizations assets and administrative activities
  2. Salaries and H R related activities
  3. Procurements
  4. Labour and equipment


THis question is out of pmbok or pmbok knowledge base - it is a Procurements - perhaPs you know procurement is people material and equipment. 
Acquisition of project team and all hired labor is a procurement . All raw material purchased is procurement all hired and purchased machines are procurements. What else remained is in house staff and office set up.
It maximum comes a 10 % of total budget.

Q1 on conflicts causes


 


Schedule, Priorities and Resources are the main causes of Conflicts among Project team. How will you describe schedule and priorities?


A.    Schedule means Staff schedule on resource calendar and Priorities means priorities of Schedule of works and activities


B.     Resource calendar is related to the causes of Resources and schedule and priorities are the same


C.    All cases except schedule and resources comes under priorities


D.    Schedule means work and activities schedule related to conflicts, and priorities means any case of priorities among individuals


 


Q 2 on communications


 Efficient communication means:


A.    How promptly a system work in response


B.    Only or most of required information is communicated


C.    How much impact of information is measured


D.    All above


 


Q3 on communications


Effective communication means


A.    Communicated in required time


B.    Communicated in required format


C.    Communicated with a required impact


D.    All above


 



 

 Hi Saket, A, B, and D.

Saket, seems I am not going anywhere much with my progress. My scores are tipping down. From 80's to mid 70's and now you just calculated a 72%. Mt exam is on Mon, what should i do ? I took simplilearn test and to my surprise scored 72% :(. Did pmzilla bonus 75 questions and scored just 50%.

Previously my scores were in late 70's to 80's. Pmstudy 1 was 80%. I have my exam approaching in just 5 days, my plan is to revise the pmbook, notes, formula and take one last mock test. Out of the 3 pmstudy tests (2-4), which one would you suggest for a final prep. And any last minute advice on what change i should be making to improve ?

Thanks, Shweta

MY best wishes to you.

Five days remained

Now you require to concentrate at PMBOK / Notes / Itto/ Formula . Be away from any lengthy MOCK test.

Take good rest /good sleep last night , and keep chocolates of your likings etcetraatcetra

Ok last mock test you may go for 4PMSTUDY.but today or tomorrow, not later.

Now your score became 9/11 = 82% , its great sign of success.

 

Thanks

 

Hey Shweta,


Please STOP taking any further mock test before you loose further confidence because of PMP exam fear. Take a day break and have some fun time with your loved ones. While having fun keep in mind PMP exam is not a roadblock in career because the worst can happen is that you fail and nothing beyond that. What if, if you fail? Simple, pay the fee again and re-try, that simple.!


I did see some of your post about your mock test performances and I do not see any need for you taking more mock test.


Just relax, read some PMPOK pages like IITO, summery when you feel like, that’s all. You know what, PMI does not put your percentage score unlike mock test, so just worry for the verdict i.e. “Pass” and nothing else.


Wish you good luck for the PMP exam.


Saket, PMP
 

Thanks Saket and Pawar. (pawarji i dont know your first name).

Thanks for the moral support and nice advice. I will just try to relax and revise my study material for the next 5 days. 

Thanks again,

Shweta

It does not matter that is he saket or pawar? or what is full name?


Its time to concentrate to exam and that you are doing.


Give most time to revisions, and making firm all maximum exam oriented areas .


There is no end of improvement, enhancing the chances right now needs to revise what you have learned.


Regards


 

Your project team members are collecting requirements in categories. They are summarising performance requirements, security requirements and technical requirements, in one category this category would be 


A.     Project requirements


B.     Product requirements


C.    Both Project and Product requirements


D.    Business requirements


 

There are various tools used for collecting requirements, regarding focus group and interviews which statement would be true among these four.


A.     Focus groups are more conversational than face to face interview


B.     Interviews involve face to face talk where focus groups involve one to all.


C.    Interviews are often conducted one on one, and become more conversational than focus groups.


D.    Interviews are typically performed asking prepared questions where focus groups involve spontaneous talks.


 

Job shadowing is a term


A.     Of human resource pulling in team Acquisition


B.     Of down time of a market due to migration of manpower to abroad


C.    Of method of a tool of collect requirement for recruiting project team


D.    Usually called as an observation technique to observe the peoples on job  


 

Prototypes are one the way for collecting feedbacks in collect requirement process, these are generally a


A.     Working model based on  progressive elaboration concept


B.     Tangible nonworking tool, a copy of future real out come


C.    3 d model for presenting in high level management meetings


D.    Ideology based mini model of a highly complex project


 

One of your team member was entering the lowest levels of Risk break down structure (RBS), in a document, he was documenting

A.    Risk register

B.    RBS

C.    Risk Checklist

D.    Risk categorization

Inaccuracy, incompleteness, instability, and inconsistency of Risk data are generally should be reviewed and re-entered during project life cycle in

A.    Risk data quality assessment

B.    Assumptions analysis

C.    Risk probability and impact assessment

D.    Risk prioritization analysis

One of the type of Information gathering technique used for Identification of risk is

A.    Root cause analysis

B.    Observations

C.    Diagramming techniques

D.    Documentation reviews

 


Feasibility Study in an organization is an important part of Business and Project, it may treated in respect of project as a


 


A.    Pre-Project Work


 


B.    Phase of The Project


 


C.    A Separate Project


 


D.    Any of the above


 

Project Governance is an approach which is responsible to make projects success and its controlling; it should be described in


A.    Project success criterion


B.    Project management plan


C.   Project Charter


D.   Project Scope


 

 


Q


Negative stakeholders have very different and conflicting objectives, you as a project manager, authorised to develop a chemical plant, how do you handle the situation with your project objectives with them:


A.   Exaggerate the principle that any project comes at ground with due sanction of Government and thus local bodies are legally bound to support the project.


B.   By balancing their interest and ensuring that project team is interacting with stakeholders in professional and cooperative manner.


C.   Motivating by this thought that every negative stake could be made in favour by serving their interest in other way.


D.   By providing and engaging project team in infrastructure and basic services developments of affected communities of surroundings.


 

Q


In collect requirement process, Requirements are defined as the needs of stakeholders, it can be defined in many ways, in one way these are


A.   Objectives of the management


B.   Other name of Deliverables


C.   Foundations of WBS


D.   Project Products


 

Operational managers are all below, from except :


A.     Core business areas


B.     Manufacturing and capital areas


C.    Maintenance departments


D.    Utilities and functional departments


At phase closure within organizations, project manager will hand off final product/ssrvice /result to


A.     Operational manager


B.     Functional manager


C.    Sponsor


D.    owner


 

Hi Pawarji, Is A the answer for the last question ?

Yes Shweta, you are very true.


I think  your exam is on 1st or 2nd of Octo.


Wish You great success.


I also understand all question at a time not possible.


Answers are here


A, A, D, A, C, B, A, D, B, B, C, D and last one is  A (All from PMBOK)


Thanks

In a matrix structure, Authority and Controlling of Project Budget are being shared by functional manager and project manager, whereas project manager is in full time role,  it is a


A.     Strong Matrix


B.     Balance matrix


C.    Weak matrix


D.    Tight Matrix


 

Many process groups exist at a time during phase or project life cycle, but generally which process group could exist throughout the life cycle along with any of the 5 process groups.


A. Planning process group


B. Executing Process Group


C. Monitoring and controlling process group


D. Closing Process group

Thanks Pawarji, yes its on 1st. Checking pmzilla forum is my break from studying :)

Next two answers, B & C. 

yes it is.

Iterative relationship is how different from overlapping relationship while in both the cases consecutive phases overlap within a project life cycle:


A.    Because in iterative relationship skilled staff and workers will be the same through the life cycle and in overlapping relationship they must be changed.


B.    Because In Iterative relationship, only one phase is planned at a time while second phase planned during execution of first phase and in overlapping relationships all phases are planned initially.


C.   In Iterative relationship, phases are undefined and varying largely by scope schedule cost etc and only one phase is planned to start and next phase is planned during the work of first phase and In overlapping relationship, phases may be entirely different in nature but they overlaps.


D.   Iterative means repeating of similar phase but not overlapping while overlapping means overlaps but not similar at all.


 

C - as others are partly correct

Here I try my best to elaborate based on pmbok knowledge base































 

PHASE TO PHASE RELATIONSHIPS


 


Iterative


Overlapping


 


 


 


1


since work by nature and outcomes remains same, though
scope, schedule, cost, place,
 contracts changes, and its successive phases becomes undefined and varying to any extend.


its phases are not similar in their nature and outcomes and they are linked in a sequence and dependent like sequential phases but unlike starting of second after one, it can overlap,


2


one phase is planned and executed,
when 1st phase in execution 2nd phase is planned.


here since phases are entirely different in nature hence they can be either planned earlier or later


3


staff, vendors and workforce may repeated same as nature of work remains same.


Staff , vender, workforce will change
as per the change in nature of work


4


Example :  research program , there is no clarity for next phase.
why it is iterative , because, research, research research -------its repetition.
Here next phase planning much depend on,
further scope as per results of 1st phase.


for example, construction may
begin when quarter design work completed.
Concept - design- construct -testing -
these are the phases and can be overlapped but not similar in nature. Here you can plan in advance or later

Q

Generally risk processes are performed in sequence of “Qualitative Risk Analysis” then “Quantitative risk analysis” then “Plan Risk Responses” but this is also true,

A.    In some cases “Perform Quantitative risk analysis” again follows Plan Risk Responses and then Monitor and Control Risk are processed.

B.    In some cases direct after Perform Qualitative Risk Analysis (without Performing Quantitative Risk Analysis), Risk Responses is planned /processed.

C.    In some cases, both “Qualitative Risk Analysis” and “Quatitative Risk Analysis” are revisited during the project‘s life cycle as to stay current with changes.

D.    All above

One of your team member engaged for Quantitative risk analysis, is using data gathering and representation technique for certain outcomes, he would be using

A.    Three point estimation technique

B.    Tree diagram method

C.    Monte Carlo Simulation

D.    Gama distribution theory

A risk was occurred at place and you are there to make funding for its contingent plan, you may be supposed as a


1.     Project manager


2.     Risk response owner


3.     Sponsor


4.     PMO


 

Fall back plan can be implemented,

A.     When the 1st strategy plan has been failed or not fully effective

B.     When accepted risk has been occurred

C.    When passive accepted risk action has been materialized

D.    When plan A has been failed or not turned as effective or an active accepted risk is occurred

 

Positive risk is if observed and management decide to implement Accept strategy, it means:

A.    Management is willing to take advantage of opportunity which comes along on the way as it is.

B.    Management will actively pursuing it, for owning it’s all possible advantages.

C.    Management will eliminate the uncertainty to ensure that opportunity could realize.

D.    All Above

Q


In the initiation stage Management was facing lot of problems and project was almost becoming unviable. Then they acquired few experts and obtained more information and changed their strategy and plan, and succeeded in their new business and project. What kind of risk strategy they adapted:


A.    Avoid


 



B.    Mitigation


 



C.   Transfer


 D. Accept

prashant.spce's picture

Dear RPS,


 


is it D.Accept?


Thanks and Regards


Prashant


 

Pages