Q framed by me from PMBOK

A project management team calls bids for procuring some customized products and for that they have to mention procurement statement of work in their request. From where they will able to develop the required procurement Statement of Work:
1. Project Charter
2. Project Scope baseline
3. Project scope statement
4. Project WBS

prashant.spce's picture

Dear RPS,


 


is it D.Accept?


Thanks and Regards


Prashant


 

A company has set up his production line but few new machines of complex nature were not working by applying after all efforts, manager suggested avoiding these machines, and using old machines which were able to give unfinished output with some defective pieces, which can be make up later, with extra efforts. What type of risk strategy he wants to develop by this way:


A.    Avoid


B.    Mitigation


C.   Transfer


D.   Accept


 


 

A trainee risk analyser was entering risk data as under,

(p) stands for Probability and ( i ) stands for Impact whereas R stands for Risk thresholds

CASE p i R =p*i
1 (-)0.30 400 (-)120
2 0.50 (-)200 (-)100
3 0.20 100 20
4 (-)0.50 (-)300 150

Which entries you will say as wrong:

A. p and i of case 4

B. i and R of case 2 and 3

C. p and R of case 1 and 4

D. p and i of all cases

 


Q


In a particular activity project manager and his/her team observed that if few skilled resources are increased, positive impact of activity will be doubled:


 


This is an example of


 


A.    Enhancing of positive risk


 


B.    Resource levelling


 


C.    Schedule compression


 


D.    Team acquisition


 

Q


Project manager was engaged with some experts and experts were assessing the effectiveness of risk responses implemented for a mega project. Expert team was busy in


1.     Risk reassessment


2.     Risk audit


3.     Variance and trend analysis


4.     Risk impact assessment


Q


Project team was busy in Identification of new risk and closing of outdated risk also they were updating current risk status by their frequent assessment. They were engaged in,


1.     Risk reassessment


2.     Risk audit


3.     Risk prioritization


4.     Risk identification


Q


Vital cause of corrective actions comes from risk process areas, is


A.     Contingent plan and workaround events


B.     Mitigated risk responses


C.    Active and passive acceptance of risk events


D.    Fall back plans and secondary risk responses


 

answers to last 12:


d,d,a,d,a,a,b,c,a,2,1,a


Please let me know.


Thanks

 I am impressed by your performance.


only 2nd q ans will be A


see my topic Torch diagram , or refer pmbok


in this questionaries -- a question on R= p*i, (page 2 last question) is quite different but from PMBOK, how you did it , can you explain.


Could I know about you. your chances are very fair.


Thanks & regards

Thanks Sir.


On the p*i question, I answered based on -ve probability. Since probability cannot be negative, the risk derived from them was also incorrect. Not sure if If it was the right logic.


My exam is scheduled on October 26th. I have been studying for last 6 weeks from PMBOK & Rita. Have started giving Mock tests from last week with below results.


Oliver 175- 82%


PMP study 100 (free)- 81%


pmpforsure 100 (free) - 72%


Though I passed in pmpforsure, this was a low score. Can you please tell me if this is an acceptable score(72%). I keep hearing that one should consistently get 80+ to be confident.


Thanks 


 

Dear Rohit,


I am just studying like you but the difference is only that since a long back I am in touch of PMP and PMzilla both, and continuely interacting with all.You can say its my style of learning and make others to get learned, in some interesting manner.


I have my own constraints. But I have a very sound experience of PM, and sometimes it works reverse in test performance.


Your logic is perfect and I am sure your performance is as good as 4ps+1p.


For Pmpforsure , it is said above 70% is equivalent of 80% of PMstudy . before of 15th attend 4-5 simulations.


edwelprogram, simplilearn, skillsign, pmzilla, examcentral not bad and 2-3 paid, etctraetctra, will make u at 5p.


be confident and be realistic


wish u all success

Q

Under Administer procurement, Procurement performance review includes

A.    Review of Quality of audits during execution

B.    Review of Buyers Inspections during seller’s execution of work

C.    Review of sellers progress to deliver projects scope

D.    All above

prashant.spce's picture

Dear RPS,


I think it is, C Review of sellers progress to deliver projects scope


 


Thanks and Regards


Prashant

it is c , reference PMBOK

Q


Firm ABC has been awarded an EPC contract under the conduct procurement process from an African country for setting a fertilizer plant, now the next step of ABC firm would be


A.     Complete the processes of  Identify Stakeholders and Collect Requirements


 


B.     Administer procurement with her contractors


 


C.    Wait for a formal order from her own country govt under Work authorization system


D.   Start execution

Answer is A

D is also correct, but it is not correct term as well as it would not be the immediate nextstep.

A === For Seller a contract is a input of Initiation - develop project charter , till win of Bid  and awarding a contract, Seller could not suppose that he or she steps in a project.

Claims Disputes and Appeals in Procurement management are due to


A.     Constructive Changes


B.     Contested Changes


C.    Both Constructive and Contested Changes


D.    Issues which are to be resolved by law and order.


 

prashant.spce's picture

Dear RPS,


 


I think it should be D.    Issues which are to be resolved by law and order.


Thanks and Regards


Prashant


 

prashant.spce's picture

Dear RPS,


 


I think it should be D.    Issues which are to be resolved by law and order.


Thanks and Regards


Prashant


 

it is c Prashant

Q 64

Procurement performance review and Inspection and audit are tools of Administer procurement, which one statement is correct in respect of an application area:

A.    Quality of audits and inspection of seller work progress is examined under Inspection and audit

B.    Verifying compliance of sellers work processes or deliverables during execution under Procurement performance review

C.    Review of sellers progress to deliver projects quality schedule cost and scope under procurement performance review

D.    In procurement performance review performed work of seller is measured while in Inspection and audit, it is checked whether quality of work is correct or not.

Ans is C

Q 65


Networking is constructive way to understand political and interpersonal factors, it impacts on


A.     Effectiveness of Business relationship, and external projects relations


B.     Effectiveness of Stakeholder relationship


C.    Effectiveness of staffing management options


D.    Effectiveness of procurement and market dealing


 Q66


Role of staffing member means:


A.     Authority belongs to member


B.     Accountability belongs to member


C.    competency owned by member


D.    Responsibility belongs to member


Q67


Responsibility Assignment matrix includes information


A.     Activities associated with a person


B.     Persons associated with an activity


C.    A Person accountable for activities


D.    All Above


 

prashant.spce's picture

Dear RPS,


My answers are:


Q.65 A.     Effectiveness of Business relationship, and external projects relations


Q.66 B.     Accountability belongs to member


Q.67 D.    All Above


 


Thanks and Regards


Prashant

Ans is CBD

prashant.spce's picture

Dear RPS,


My answers are:


Q.65 A.     Effectiveness of Business relationship, and external projects relations


Q.66 B.     Accountability belongs to member


Q.67 D.    All Above


 


Thanks and Regards


Prashant

 


Q


A responsibility description documents providing information regarding, Responsibility, Accountability, Competency, and Qualification, would be a


A.     Role-Responsibility-Authority Form


B.     RACI Chart


C.    Organizational Chart


D.    Histogram Chart


 

prashant.spce's picture

Dear RPS,


 


I think the answer is B.RACI Chart


Thanks and Regards


Prashant

prashant.spce's picture

Dear RPS,


 


I think the answer is B.RACI Chart


Thanks and Regards


Prashant

its A, read pmbok very soon you will catch these all

A project team member working in human resource department was searching for the strategic information regarding Human resource policies, Union contracts and regulations, as a project manager what you will suggest to get them at one place:

A.    Organizational process assets

B.    Staffing management plan

C.    Enterprise Environmental factors

D.    Project management information system

Ans is B

 


Q


In a risk analysis a team member assessed the probability of a risk is as “one”, it means:


1.     It is a 100% risk


2.     It is a pure opportunity


3.     It is a pure risk


4.     It is a certain event


 

this is a tricky question and answer would be D.

 


Q


Which one is Uniform Distribution Method graph


 Refer below link for figures


er-sspawar.blogspot.in/2012/10/this-page-contains-javascript-functions.html


or


er-sspawar.blogspot.in

I hope somebody will answer this question definitely.

Q


In quantitative risk analysis, different probability distribution methods are used, below figure is an examplw of:



  1. Normal Distribution Method

  2. Discrete Distribution Method

  3. Uniform Distribution

  4. Triangular Distribution





















































































































Y axis showing probablity                  
                 
50%                
               
40%            
           
30%          
           
20%          
         
10%        
  $10 $20 $30 $40
  X axis - showing cost            

Ans is 2., here all data could not be defined under any probablity curve, hence it is discrete data.

A project team of 20members including Project head, having mobile hand set each and in addition of handsets, 5 seniors have individual land line phones and remaining staff is using 2 land line phones commonly. How many potential communication channels you will consider.

A. (20X2 ) + (7X2)

B. (19x10) +(7x3)

C. (20+5+2) x13

D. (19x10)

 Nobody nowhere will find such critical unique question on communication channels.

Actually it is framed by me from, a real world scenario and PMBOK .

How you can corelate both practical and guide.

By this example, my aim is to make understanding what are channels.

what will be the answer.

Read PMBOk and select your choice,

 

warm Regards

In a basic communication model, various standard terms and their functions are defined. Which statement in this reference is NOT correct?
A. Sender is not responsible whether message has been understood by receiver.
B. Lack of back ground information, Distance and unfamiliar technologies are Noises
C. Message is output of sender and feedback message is output from receiver.
D. Method used to decode the message is called Medium.

prashant.spce's picture

Dear RPS,


I think,the answer is D.Method used to decode the message is called Medium.


 


Thanks and Regards


Prashant

Thanks Prashant definitely  answer is D as well as C also.


actually My aim was the C .


But by mistake option D has written wrongly:


D. Method used to decode the message is called Medium.


in place of decode , I had thought I had written convey


and if Write convey


option will be

D. Method used to convey the message is called Medium.


 


then only option C will be the answer.


thank you for making me right


Actually by this question my intension was that Message and feedback message both are output of sender. hence option C is not correctly worded, and it will be the appropriate answer.


Q
As an organizational process asset updates, Project reports, are output of Distribute information process, it includes project status and following all except:
A. Minutes of meetings
B. Project closure reports
C. Issue logs
D. Lesson learned

Q
Project Note Book is
A. A document belongs to Sponsor, which keeps all summary notes during projects.
B. A document belongs to Project team, which keeps records like memo, correspondences, projects’ other records
C. A document of Project manager, which keeps all relevant and confidential reports to help him/her during project works.
D. An electronic data point kept in project management information system and updated regularly.

Ans is A and B

Q
Being a Project manager, to distribute performance report, which communication method, you will prefer:
A. Interactive communication Method
B. Push communication method
C. Pull communication method
D. Formal written

prashant.spce's picture

Dear RPS,


As per my knowledge, answer should be D. Formal written


 


Thanks and Regards


Prashant

Prashant please read last line of P269/300 PMBOK 4

Work performance information is an output of direct and manages project execution, it comprises following information except


A.     Deliverables status


B.     Schedule progress


C.    Cost incurred


D.    WBS updates


 

wbs updates is not a part of wpi


wpi is not an updating submission , its a information as raw data


wbs is planning item, it will updated there.


other 3 are mentioned in pmbok explicitly.


hence D,

Q

To manage risks and implement risk responses activities 

is part of which process group:



  1. planning 

  2. executing

  3. monitoring & controlling

  4. initiating

it is executing


identification, plan, develop done in planning


manage / implement in execution


monitor and control in M&C