Earned Value management Question
Submitted by taifii on Fri, 06/28/2013 - 14:13
If one Project should complete in 10000 $ and required number of hours 1200 with hourly labour cost 150 per hour.
But In actually they reach the cost 8000$ and number of hours spend 1400 with hourly labour cost 150per hour so what will be Earned Value.
Forums:


taifii
Fri, 06/28/2013 - 17:28
Permalink
Confuse about this Question
I am confuse about this question, you can expect such kind of questions in exam..... :-(....This scanario based on what we will no how much actual work performed...???
cnppmp
Sat, 06/29/2013 - 13:11
Permalink
$154800?
$154800?
Regards
CN Patil
taifii
Sun, 06/30/2013 - 08:18
Permalink
Please share the calculation Method
Hi Patil,
How did you calculate, would you please share...
Thanks
humanbeing2001
Sat, 06/29/2013 - 18:40
Permalink
How did you arrive at 154800.
How did you arrive at 154800.
loma
Sun, 06/30/2013 - 09:29
Permalink
218000 ??
Not fully sure, but here using EV=%compl*BAC
so EV=100%*(cost+labour cost)=8000+(1400*150)= 218000
humanbeing2001
Mon, 07/01/2013 - 06:28
Permalink
After giving many thoughts in
After giving many thoughts in the question,
162857
Please let me know if this is the right answer.
alexalburca
Mon, 07/01/2013 - 19:02
Permalink
the question is poorly
taifii
Mon, 07/01/2013 - 20:33
Permalink
Can not be calculated..
Agree .Can not be calculated
humanbeing2001
Tue, 07/02/2013 - 10:01
Permalink
please provide the option?or,let me reveal my way of calculation
Dear Taifii, Could You please provide the options? If You can't, then let me reveal my way of calculation,
SPI= Schedule performance Index which shows the Schedule performance with respect to Cost. Here we can exptrapolate the same thru time (if you want to have any calcualtion).
Planned Time = 1200 Hours, Actual Time Taken =1400 Hours,
In actual 1 unit planned has been done at 1200/1400 unit of actual work. (SPI)
PV = 10000+1200*150 = 190000
EV = PV * SPI = 190000 * 1200/1400 = 162857.
This is How EV can be arrived.