Earned Value management Question

taifii's picture

 If one Project should complete in 10000 $ and required number of hours 1200 with hourly labour cost 150 per hour.

But In actually they reach the cost 8000$ and number of hours spend 1400 with hourly labour cost 150per hour so what will be Earned Value.

taifii's picture

I am confuse about this question, you can expect such kind of questions in exam..... :-(....This scanario based on what we will no how much actual work performed...???

cnppmp's picture

$154800?

 

Regards

CN Patil

 

 

taifii's picture

Hi Patil,

How did you calculate, would you please share...

Thanks 

How did you arrive at 154800.

Not fully sure, but here using EV=%compl*BAC

 

so EV=100%*(cost+labour cost)=8000+(1400*150)= 218000

After giving many thoughts in the question,

162857

 

Please let me know if this is the right answer.

the question is poorly worded!
 
First the planned value should hit with the hours spent.
 
  1200 hours * $ 150 per hour: the result would be $ 180,000
 
how he spent $ 8,000 on 1400 hours and $ 150 per hour .. is not no way!
 
how to calculate something? there is no way?
 
 
 
 
taifii's picture

 Agree .Can not be calculated

Dear Taifii, Could You please provide the options? If You can't, then let me reveal my way of calculation,

 

SPI= Schedule performance Index which shows the Schedule performance with respect to Cost. Here we can exptrapolate the same thru time (if you want to have any calcualtion).

Planned Time = 1200 Hours, Actual Time Taken =1400 Hours,

In actual 1 unit planned has been done at 1200/1400 unit of actual work. (SPI)

PV = 10000+1200*150 = 190000

EV = PV * SPI = 190000 * 1200/1400 = 162857.

This is How EV can be arrived.