What is the EAC for the project
Submitted by steelproject2012 on Sun, 02/10/2013 - 12:06
Forums:
Activity A is worth $800, is 100% complete, and actually cost $800. Activity B is worth $300, is 90% complete, and actually cost $480 so far. Activity C is worth $800, is 75% complete, and has cost $700 so far. The total budget is $4,000. What is the estimate at completion for the project?