Qustion on PERT Submitted by henrypmp123 on Sun, 02/10/2013 - 11:57 Forums: PMP / CAPM exam Question bankGiven the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely6 days, what is the PERT weighted average?A. 6B. 4C. 6.3D. 6.1