ETC and PV
Submitted by steelproject2012 on Sun, 02/10/2013 - 11:47
Forums:
(1) Activity A is worth $200, is 100% complete, and actually cost $200. Activity B is worth $75, is 90% complete, and actually cost $120 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1,000. What is the estimate to complete for the project?