Compromise Vs Smoothing
Submitted by nirupamasai on Tue, 08/17/2010 - 08:50
Forums:
Hi,
I want answer for this following question
1) Two project members are in disagreement
2) Project manager advises the members to arrive a solution which will have best features of both approaches
3) What is the conflict resolution technique
I chose smoothing because Project manager focuses areas of agreement but answer given is Compromise. Which is the correct conflict resolution for this problem?