Oliver 175 Q Set ( Please explain Q : 94:
Submitted by sai_murthy on Wed, 08/18/2010 - 03:34
Forums:
The duration uncertainity - defined as pessimistic minus optimistic estimate - of the first activity is 18 days and the second estimate has uncertainity of 24 days . Applying PERT formula fo rpaths , what is the duration uncertainity of the entire path
a. 21 d
b. 30 d
c. 42 d
d. No statement is possible