Work performance information vs Work perforkmance Measuremnt

I have competed 10 floors of a building- for me this a WPI

I am supposed to complete 100 floors when the project completes - thus i am 10% complete

is this WPI or WPM?

As planned in should have completed 30 floors by today so compared to the planned have completed 33 % of the planned work - this is a WPM

My variance is 66% or 20 floors, this is a variance.

 

So i am lost with point 2 the 10% completeor the status is it WPI or WPM