Work performance information vs Work perforkmance Measuremnt
Submitted by joe_aad on Thu, 05/10/2012 - 12:14
Forums:
I have competed 10 floors of a building- for me this a WPI
I am supposed to complete 100 floors when the project completes - thus i am 10% complete
is this WPI or WPM?
As planned in should have completed 30 floors by today so compared to the planned have completed 33 % of the planned work - this is a WPM
My variance is 66% or 20 floors, this is a variance.
So i am lost with point 2 the 10% completeor the status is it WPI or WPM