WBS - Question !!
Submitted by sam_jain on Wed, 05/09/2012 - 04:28
Forums:
The WBS is an input to all of the processes EXCEPT:
A. Scope verification
B. Cost estimating
C. Activity definition
D. Plan purchases and acquisitions
E. Cost budgeting
Correct Answer : A
My Answer --> WBS is an input to all the above processes - directly or indirectly ( Scope Baseline)
Please advise.
Regards,Sam