question from FastTrack
Submitted by moxir on Fri, 06/15/2012 - 14:41
Forums:
Hi,
Just an info on this question that is quite easy but i don't get it.
Which of the following you DON'T need to do if there is a major delay on a NON critical path activity?
a) investigate delay NOK
b) revaluate which path is critical NOK
c) change the project schedule OK
d) review the float time for the activity NOK
I have selected c) since i though i need to reestimate the critical path after some activity time si changed.. wasn't it?
