Which of the following you DON'T need to do if there is a major delay on a NON critical path activity?
a) investigate delay NOK
b) revaluate which path is critical NOK
c) change the project schedule OK
d) review the float time for the activity NOK
I have selected c) since i though i need to reestimate the critical path after some activity time si changed.. wasn't it?
Forums:


projmanpro
Fri, 06/15/2012 - 16:19
Permalink
Your choice "C" is correct.
Your choice "C" is correct. this is the thing we "DONT" need to do as asked in the question.