Project risk question

 Hi , 

Whie answering some questions i found this :

 

Project risk should be identified by :

a- those invited to the risk identification process only

b- the project stakeholders only

c- the project manager only 

d- all the project personnel 

 

 

i answered  B , but the right was D 