Risk response, where it is implemented
Submitted by rameshkr on Tue, 10/18/2011 - 09:30
Forums:
As per PMBOK section 4.3 Direct and Manage Project Execution also lists - the manage risks and implement risk responses activities. (page 83 PMBOK guide)
But the same activity (risk response implementation) is part of the Monitor and Control Risks process.
So, where exactly is the implementation takes place?