Question from PMStudy Exam

In your construction project, the CPI is 0.85 and SPI is 1.25. What could be the possible reason?

 
     1     A critical resource went on sick leave for a long period of time, which had not been anticipated earlier.
 
     2     The cost of raw materials required for construction increased by 10%. - You had anticipated a cost increase of 12% in your project plans.
 