Question on Mean

This is a question from rita fast track.

You just completed a cost estimate on the project, and you are assuming that there is a 15% chance you will exceed this estimate. You are:

a Below the mean

b. Above the mean

c. Above the median

d. Belotthe median

Please let me know the rational behind the answer and how can i understand more about this question.

 