Help please for this question from Oliver Lehmann
Can someone help me with this question?
Q94-Together with your team, you applied three-point estimation on a critical path
which consists of two activities.
The following duration uncertainties are all calculated assuming a ±3sigma
confidence interval.
The duration uncertainty—defined as pessimistic minus optimistic estimate—of
the first activity is 18 days; the second estimate has an uncertainty of 24 days.
Applying the PERT formula for paths, what is the duration uncertainty of the