projected cost performance
Submitted by Anonymous (not verified) on Sat, 01/05/2013 - 20:31
Forums:
You have calculated the projected cost performance that must be achieved on the remaining work to meet a specified goal. This projected cost performance is also known as
Choice 1 Performance measurement document
Choice 2 To-complete performance index