Earned value question
Submitted by riyaz145 on Mon, 01/07/2013 - 13:39
Forums:
After analyzing the status of your project, you determine that the EV is lower than PV. What should you expect if this trend continues?
1. The actual cost will be lower than planned
2. the EAC will be lower than planned
3. The project will finish behind schedule
4. The project will finish below the original cost estimate.
Kindly explain the reasoning behind the answer. Thanks.