You are managing the project when you discover an estimated completion date will occur after the desired date. What should you do FIRST?
1. Add resources to the project
2. Evaluate the possibility of doing more activities in parallel.
3. Negotiate for more time
4. Explain to the customer that the project cannot be done on time.