what will you do?

You have been working on a project for the last six months. Your management lets you know that you will receive an incentive of $ 5,000, if you complete the project one month ahead of schedule. When closing the project ahead of schedule, your team informs you that the product contains 

 

a minor flaw and may not fully satisfy the customer`s needs. However, rectification of the minor flaw will require a lot of changes and take 2 more months. In this context, you will: 

 