Small Project Question
Submitted by raza82 on Mon, 02/04/2013 - 12:24
Forums:
You are managing a small project with five team members working part-time.
At the beginning of every week, you orally allocate work to all the team members.
This is an example of:
Choice 1 Work Authorization System
Choice 2 Improper Planning because team members do not know in advance what needs to be done at what time