Discretionary Dependencies
Submitted by PMPism on Sat, 08/06/2011 - 14:27
Can someone please explain me with some examples if possible to help understand this statement " Discretionary Dependencies can limit later scheduling options since they can create arbitrary total float values hence should be fully documented."
Thanks
Forums:
bhpepper
Sat, 08/06/2011 - 23:36
Permalink
A discretionary dependency is
"A discretionary dependency is one that isn't based on a "have to", but on a "should". These decisions are usually based upon best practices, business knowledge, etc. They are placed on the project diagram where the team members would like them to occur.
Since discretionary dependencies are more arbitrary, they should be fully documented so the reasons for their placement can be maintained and available during future revisions. As a project progresses and adjustments are needed, discretionary dependencies are often reviewed for possible alterations."
http://forums.oreilly.com/topic/49556-pmp-exam-tip-what-is-the-differenc...
PMPism
Sun, 08/07/2011 - 18:53
Permalink
Thanks so much... this was
Thanks so much... this was really helpful !!
Rita Stowers
Mon, 10/23/2017 - 19:43
Permalink
Education is the key factor
Education is the key factor and everyone must get an education to secure future. The students who wanted to PMP certificated they must visit the best dissertation.com website for helping material. I’m sure the professionals and the capable person can help in studies.
happynewyear18
Thu, 12/07/2017 - 06:06
Permalink
happy new year 2018
someone please explain me with some examples if possible to help understand this statement " Discretionary Dependencies can limit later scheduling options since they can create arbitrary total float https://www.happynewyear365.com/advance-happy-new-year-2018-wishes/ values hence should be fully
pmalik
Fri, 12/08/2017 - 05:08
Permalink
All About Dependencies
To know more about Dependency, you can read this article:
https://www.pmbypm.com/4-types-of-project-dependencies/
jamtopics
Fri, 12/08/2017 - 05:32
Permalink
jam topics
Interview Jam Topics for Interview: JAM round just a minute topics is basically an eligibility test in an interview where you are supposed to speak on a topic. The topic may range from a variety of things but all you Jam sessions topics need to do is appear confident
goldratetoday
Sat, 12/09/2017 - 05:35
Permalink
gold rate today
as well as the dividend payouts, these two gold miners would have an even higher production cost. But, that would still not change the overall production Gold rate today all that much
amilaa255
Tue, 12/26/2017 - 15:06
Permalink
Amazing Article.
I really enjoy simply reading all of your weblogs. Simply wanted to inform you that you have people like me who appreciate your work. Definitely a great
post. Hats off to you.
Advance Happy New Year Images
Happy New Year 2018 HD Wallpapers Download
Happy New Year 2018 Images Download
Happy New Year 2018 GIF Images Free
amilaa255
Fri, 01/19/2018 - 07:42
Permalink
Amazing Article.
Your post has many detail information. I read all of your article and I genuinely like it. Thank you for discussing this great post. Happy Valentines Day Images 2018
Happy Valentines Day 2018 Quotes
Happy Valentines Day Week List 2018
Funny Valentines Day Messages for her
Valentines Day Whatsapp DP 2018