Time management question
Submitted by NISHA on Fri, 06/26/2015 - 19:36
Hey Guys..
Please help me to answer this question.
- A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
- Finish-to-Start
- Start-to-Finish
- Start-to-Start
- Finish-to-Finish
Thanks
Nisha
Forums:


deepaklondhave
Fri, 06/26/2015 - 22:23
Permalink
ANSWER
Finish to start
NISHA
Sat, 06/27/2015 - 05:02
Permalink
Thank you
Hello Deepak,
Thank you for your answer and this is the right answer but If we are saying the "A schedule activity may begin 10 days before the predecessor activity finishes"
Shouldnt it be the answer start to finish becuase in finish to start we can start the next activity only when the predesessor will be finish.We are accelerating the successor activity here.
Please let me know your thoughts.
Regards
Nisha
gomsy
Mon, 06/29/2015 - 23:00
Permalink
Time management question
HI Nisha,
I think Deepak is right here... Its the lead in F-S relation.
ngufo06
Tue, 06/30/2015 - 04:30
Permalink
i really doubt why it is FS..
i really doubt why it is FS.....why can't it be SS
Activity B can start if A has started ....consider is lead with 10 days
NISHA
Tue, 06/30/2015 - 06:46
Permalink
Source of this question
Hello Guys..
Source of this question is below ques. no. 6.
http://preparepm.com/pmp/schedule.html
Nisha
admin
Wed, 07/01/2015 - 03:09
Permalink
Since the Start of successor
Since the Start of successor is linked to finishing of Predecessor its Finish to start.
In start to Finish - B can't finish before A starts . This constraint is not imposed in the question.
NISHA
Wed, 07/01/2015 - 05:59
Permalink
Thank you admin..
Thank you..for the clarification..I really appreciate that..
Thank you very much..
Nisha..