Question on project close
Submitted by philzs on Tue, 03/17/2015 - 00:06
128 - Which one of the following is the last step of project closing
A ) Archive project documents
B ) Measure customer satisfaction at the end of the project
C ) Client appreciates your product
D ) Lessons Learnt are documented
What do you think and why :-)
Forums:


admin
Tue, 03/17/2015 - 05:42
Permalink
http://pmzilla.com/when-do
http://pmzilla.com/when-do-release-resources-project
Search on PMZilla for "Closing sequence"
Also check. http://pmzilla.com/simplilearn-question-closing-sequence then you can post your response here.
coolpmp69
Tue, 03/17/2015 - 13:50
Permalink
A ) Archive project documents
A ) Archive project documents
philzs
Wed, 03/18/2015 - 19:58
Permalink
From simplilearn answer is B,
From simplilearn answer is B,
I am not sure this is actually the right answer
akbar.azwir
Fri, 03/20/2015 - 17:08
Permalink
In my opinion, A and D is
In my opinion, A and D is identical or the same thing. C is plainly incorrect. So that leaves us with B.
rekhasharma30
Fri, 03/20/2015 - 23:38
Permalink
Archive document would be
Archive document would be correct answer
lfc3388
Fri, 03/20/2015 - 19:06
Permalink
D
According to Rita, Its D. Archiving project documents comes before LL.
philzs
Fri, 03/20/2015 - 21:28
Permalink
Admin, what do you think on this one,
Admin, what do you think on this one, there is a lot of different opinion here
PP-PMP2014
Mon, 03/23/2015 - 16:51
Permalink
My Ans is A
Reason : Archive Project Docuemnt contains Lesson Learnt as well ther are many more documents which u need to archive along with lesson learn.
Measure customer satisfaction is done before taht....
Last thing which u do in closing is release the team and just before doing that u archive project documents.
So the ans is A.
jyotig
Wed, 03/25/2015 - 11:17
Permalink
Answer is A
The correct answer is A.
Sharing a link for better understanding of this topic close project
https://www.youtube.com/watch?feature=player_embedded&v=CJongXKL91A
Thanks!