Question on project close

128 - Which one of the following is the last step of project closing

A ) Archive project documents

B ) Measure customer satisfaction at the end of the project

C ) Client appreciates your product

D ) Lessons Learnt are documented

 

What do you think and why :-)

admin's picture

http://pmzilla.com/when-do-release-resources-project

Search on PMZilla for  "Closing sequence"

Also check. http://pmzilla.com/simplilearn-question-closing-sequence then you can post your response here.

A ) Archive project documents

From simplilearn answer is B,

 

I am not sure this is actually the right answer

akbar.azwir's picture

In my opinion, A and D is identical or the same thing. C is plainly incorrect. So that leaves us with B.

Archive document would be correct answer

According to Rita, Its D. Archiving project documents comes before LL.

Admin, what do you think on this one, there is a lot of different opinion here

Reason : Archive Project Docuemnt contains Lesson Learnt as well ther are many more documents which u need to archive along with lesson learn.

Measure customer satisfaction is done before taht....
Last thing which u do in closing is release the team and just before doing that u archive project documents.

So the ans is A.

The correct answer is A.