LAST activity to perform while closing a project
Submitted by MANOJ RAMRAOJI ... on Thu, 06/06/2013 - 10:50
Which of following is the LAST activity to perform while closing a project?
a) creating lesseons learned
b) releasing resourses assigned to the project
c) verify scope
d) close procurement
Forums:


admin
Thu, 06/06/2013 - 11:19
Permalink
Search pmzilla for 'closing
Search pmzilla for 'closing sequence"
cnppmp
Thu, 06/06/2013 - 11:34
Permalink
B
Desecending Order
releasing resourses assigned to the project
Creating lessons learned
Close procurement
Verify scope
MANOJ RAMRAOJI ...
Fri, 06/07/2013 - 05:09
Permalink
D
Close procurement or Project is the last ACTIVITY to be performed.
bkthakkar
Fri, 06/07/2013 - 06:29
Permalink
There will be many
There will be many procurements within the Project which require closure before the complete project is completed and hence the option of Close Procurment is ruled out.
For any project as rightly pointed by CNP among the options given in the question, releasing the resources will be the last activity. You require resources for writing the lessons learned. Therefore, releasing the same is the last activity after the project is completed