LAST activity to perform while closing a project

Which of following is the LAST activity to perform while closing a project?

a) creating lesseons learned

b) releasing resourses assigned to the project

c) verify scope

d) close procurement

admin's picture

 Search pmzilla for 'closing sequence"

cnppmp's picture

 


Desecending Order


releasing resourses assigned to the project  


Creating lessons learned


Close procurement


Verify scope

Close procurement or Project is the last ACTIVITY to be performed.

There will be many procurements within the Project which require closure before the complete project is completed and hence the option of Close Procurment is ruled out.


For any project as rightly pointed by CNP among the options given in the question, releasing the resources will be the last activity.  You require resources for writing the lessons learned. Therefore, releasing the same is the last activity after the project is completed