no. of critical paths

1)      If the number of critical paths in the project increases, but the duration of the project remains the same, what should the project manager do?

  1. Perform crashing to complete project on time
  2. Fast track the project
  3. Perform additional risk planning
  4. Decrease the scope of the project

This could be 3. More no of critical paths causes more risks.

right it is 3

 Yes, option 3 is right

jvleminc's picture

Should be 3.

Project duration stays the same -> 1, 2 and 4 are unneeded. 

cnppmp's picture

addtional risk planning, may be executing the (Quantitative analysis) simulation techniques (Monte Carlo), if the option provided for tools, I think this would have been fitted as well.


Regards


CN Patil, PMP