project phase Qn

 


You have been managing a project to construct a flyover. You have divided the project into phases to provide better management control. Which of the following is a characteristic of a project phase? 

 

 

Choice 1

Formal phase completion necessarily includes authorization for the subsequent phase.

 

 

Choice 2

A project phase can be closed with a decision not to initiate the subsequent phase.

 

 

Choice 3

A project phase should not be divided into sub-phases even in complex projects, because it will be difficult to manage.

 

 

Choice 4

All deliverables in the project phase should correspond to the project management process.

 

 

crushPMP's picture

Will go with 4


1 - Does not make sense as no formal authorization is needed to go from P1 to P2


2 - Could be possible


3 - Not true


4 - Definitely

 I go with 2.

I think the question is missing NOT.

 

Except C, all 3 are charactors of a Phase.

 

Which of the following is a characteristic of a project phase? 

 my ans is D,

provided

Choice 4

All deliverables in the project phase should correspond to the project management process processes.

Choice 1 - it is not necessary that completion of any phase is a authorisation for subsequent phase. subsequent phase may be started earlier or may be sarted later by seperate authorization.

Choice 2 - it is not necessary , that if further phase is not needed, present phase will be closed .( here closed means may be terminated )

Choice 3 - project or phases can be divided in sub project or subphases as per pmbok.

hence option 1, 2 and 3 are not the characterstics of phases.

Choice 4 - as per pmbok any phase follow the project management processes and complete the corresponding deliverables.