project phase Qn
|
You have been managing a project to construct a flyover. You have divided the project into phases to provide better management control. Which of the following is a characteristic of a project phase? |
|
|
|
|
||
|
Choice 1 |
Formal phase completion necessarily includes authorization for the subsequent phase. |
|
|
|
||
|
Choice 2 |
A project phase can be closed with a decision not to initiate the subsequent phase. |
|
|
|
||
|
Choice 3 |
A project phase should not be divided into sub-phases even in complex projects, because it will be difficult to manage. |
|
|
|
||
|
Choice 4 |
All deliverables in the project phase should correspond to the project management process. |
|


crushPMP
Tue, 05/07/2013 - 15:44
Permalink
Will go with 4 1 - Does not
Will go with 4
1 - Does not make sense as no formal authorization is needed to go from P1 to P2
2 - Could be possible
3 - Not true
4 - Definitely
rwmv
Tue, 05/07/2013 - 16:44
Permalink
Answer:2
I go with 2.
Jgrind07
Tue, 05/07/2013 - 21:29
Permalink
I think the question is
I think the question is missing NOT.
Except C, all 3 are charactors of a Phase.
sspawar
Tue, 05/07/2013 - 23:32
Permalink
Which of the following is a
Which of the following is a characteristic of a project phase?
my ans is D,
provided
Choice 4
All deliverables in the project phase should correspond to the project management
processprocesses.Choice 1 - it is not necessary that completion of any phase is a authorisation for subsequent phase. subsequent phase may be started earlier or may be sarted later by seperate authorization.
Choice 2 - it is not necessary , that if further phase is not needed, present phase will be closed .( here closed means may be terminated )
Choice 3 - project or phases can be divided in sub project or subphases as per pmbok.
hence option 1, 2 and 3 are not the characterstics of phases.
Choice 4 - as per pmbok any phase follow the project management processes and complete the corresponding deliverables.