what is the next process?

 A project team is in the planning stage and they have completed creating the work breakdown structure for the project. Which of the following process can they start NEXT?

A)Define Activity

B)Estimate Cost

C)Determine Budget

D)All of the above 

crushPMP's picture

A. Perform "Define Activity" to break the Work Packages into Activity List, Activity Attributes and Milestone Lists

A.

A

 Yes, I too have answered as A. But the answer is given as D (All of the above). How is it possible?

crushPMP's picture

Definitely not true, must be an erreta.

 Yes, true. Thank You

 I answered option D as all those options mentioned begin after creating WBS.

 Question does not ask " What is next". It says which of the following process is next? So the answer should be D-all those activities.

Can we start Determine Budget after WBS?


Can we start Estimate after WBS?

 4TH PARA 1ST 2LINES , CH 7, - SAYS ANS  D

Qn is asking Which process can they start NEXT..

I would have gone with option A...

How can we estimate cost without decomposing

Work packages to activity level, and that is done in Define activity process.

Any thought? 

crushPMP's picture

Clearly a dumb question. Ans is A, time to move on and not waste any more bandwidth on this useless topic.


Next question please...