A project team is in the planning stage and they have completed creating the work breakdown structure for the project. Which of the following process can they start NEXT?
A)Define Activity
B)Estimate Cost
C)Determine Budget
D)All of the above
Forums:


crushPMP
Mon, 05/06/2013 - 17:01
Permalink
A. Perform "Define Activity"
A. Perform "Define Activity" to break the Work Packages into Activity List, Activity Attributes and Milestone Lists
vn
Mon, 05/06/2013 - 17:02
Permalink
Answer is
A.
eng_mut
Mon, 05/06/2013 - 17:08
Permalink
A
A
vijayavadrevu
Mon, 05/06/2013 - 17:10
Permalink
Yes, I too have answered as
Yes, I too have answered as A. But the answer is given as D (All of the above). How is it possible?
crushPMP
Mon, 05/06/2013 - 17:12
Permalink
Definitely not true, must be
Definitely not true, must be an erreta.
vijayavadrevu
Mon, 05/06/2013 - 17:15
Permalink
Yes, true. Thank You
Yes, true. Thank You
rwmv
Mon, 05/06/2013 - 17:33
Permalink
D is correct
I answered option D as all those options mentioned begin after creating WBS.
rwmv
Mon, 05/06/2013 - 17:35
Permalink
It is D
Question does not ask " What is next". It says which of the following process is next? So the answer should be D-all those activities.
y0zh
Tue, 05/07/2013 - 13:05
Permalink
Can we start Determine Budget
Can we start Determine Budget after WBS?
Can we start Estimate after WBS?
sspawar
Tue, 05/07/2013 - 14:20
Permalink
4TH PARA 1ST 2LINES , CH 7,
4TH PARA 1ST 2LINES , CH 7, - SAYS ANS D
BK
Tue, 05/07/2013 - 14:33
Permalink
Qn is asking Which
Qn is asking Which process can they start NEXT..
I would have gone with option A...
How can we estimate cost without decomposing
Work packages to activity level, and that is done in Define activity process.
Any thought?
crushPMP
Tue, 05/07/2013 - 14:35
Permalink
Clearly a dumb question. Ans
Clearly a dumb question. Ans is A, time to move on and not waste any more bandwidth on this useless topic.
Next question please...