What part of the porject management process is

The project manager is making sure that the product of the project has been completed according to the project management plan. What part of the porject management process is he in?

 close

it's per Rita answer. But I believe that project plan result finishes within Executing process with providing deliverable and send it to Verify scope. Can you please provide any reference in PMBOK which refers to close?

 P99/100

Content is telling - execution has been completed,

Hi Pawarji,


Im seeing the term Product verification in aother test books. In PMBOK it is not evident.


Q is ,


 Is Product verification a part of Close Project  as well in Close Procurements processes ?


regards


Renji

Closing - Question suggests there is a completed product. Completed products are subject to scrutiny in only the following two processes:

1) Close Project/Phase

2) Close Procurement

Shouldn't this come in Verify Scope which happens in Monitoring and Controlling Process Group ?