What part of the porject management process is
Submitted by y0zh on Fri, 03/29/2013 - 10:24
The project manager is making sure that the product of the project has been completed according to the project management plan. What part of the porject management process is he in?
Forums:


sspawar
Fri, 03/29/2013 - 14:46
Permalink
close
close
y0zh
Fri, 03/29/2013 - 18:12
Permalink
it's per Rita answer. But I
it's per Rita answer. But I believe that project plan result finishes within Executing process with providing deliverable and send it to Verify scope. Can you please provide any reference in PMBOK which refers to close?
sspawar
Sat, 03/30/2013 - 01:30
Permalink
P99/100
P99/100
Content is telling - execution has been completed,
Renji2013
Sun, 03/31/2013 - 12:51
Permalink
Product verification ?
Hi Pawarji,
Im seeing the term Product verification in aother test books. In PMBOK it is not evident.
Q is ,
Is Product verification a part of Close Project as well in Close Procurements processes ?
regards
Renji
sandeshkd
Tue, 06/18/2013 - 03:16
Permalink
Answer
Closing - Question suggests there is a completed product. Completed products are subject to scrutiny in only the following two processes:
1) Close Project/Phase
2) Close Procurement
rjbuzzing
Mon, 07/01/2013 - 00:10
Permalink
Shouldn't this come in Verify
Shouldn't this come in Verify Scope which happens in Monitoring and Controlling Process Group ?