TCPI

Please check this question for TCPI from Pmstudy.

http://www.pmzilla.com/tcpi

My ans came as 1.(i considered atypical variance to calculate TCPI)

So I wanted to conform here,

when there is no specification of the scenario  we should go for BAC/CPI for EAC calculation?

Please let me know.

 

 

 I saw that question.

Yes both answer may true , bks how will be the future performance of project - typical or Atypical - is not mentioned, 

then what we need to consider in exam,BAC/CPI as default?

If no deviations are mentioned, assume the project is going well under a good PM!


So EAC = BAC / CPI