TCPI
Submitted by sunitaPMP on Wed, 03/06/2013 - 23:02
Please check this question for TCPI from Pmstudy.
My ans came as 1.(i considered atypical variance to calculate TCPI)
So I wanted to conform here,
when there is no specification of the scenario we should go for BAC/CPI for EAC calculation?
Please let me know.
Forums:


sspawar
Wed, 03/06/2013 - 23:58
Permalink
I saw that question.Yes both
I saw that question.
Yes both answer may true , bks how will be the future performance of project - typical or Atypical - is not mentioned,
sunitaPMP
Thu, 03/07/2013 - 00:32
Permalink
then what we need to consider
then what we need to consider in exam,BAC/CPI as default?
Renji2013
Fri, 03/29/2013 - 08:32
Permalink
Typical should be
If no deviations are mentioned, assume the project is going well under a good PM!
So EAC = BAC / CPI