PMP mock questions
18) You just found out that the company that you were planning to use in your project is known for being late in delivering their products that can lead to losses to the project. You decide to go with a different company to ______ the risk ?
a) Mitigate
b) Reject
c) Transfer
d) Avoid
111) Actual cost=$1000, Budget at completion=$800, cost performance index=0.5, Earned value= $600, the variance can occur again. The estimate at completion is:
a) $1000
b) $1400
c) $800
d) None of the above
"the variance can occur again" what does this means ? typical or atypical not sure.
138) Arrow diagramming method does not use: a) Float b) Finish to start relationship c) Lag d) Activities
147) The difference between maximum funding and the end of cost baseline is:
a) Management reserve
b) Cost baseline
c) Cost overrun
d) None of the above
154) Tannenbaum and Schmidt continuum proposes:
a) Five stages of team development
b) Model-telling
c) Offering more freedom as the team matures
d) None of the above
I did never come across continuum process in PMBOK or other book. any idea what it is?
195) Regarding control limits, which of the following is true:
a) If a point lies outside of the control limits, or seven consecutive points are on one side of the mean but within control limits, the process is out of control
b) If a point lies outside of the control limits, or seven consecutive points are on either side of the mean but within control limits, the process is out of control
c) If all but seven points lie within the control limits, and seven consecutive points are on one side of the mean but within control limits, the process is in control
d) None of the above


sspawar
Tue, 02/26/2013 - 09:25
Permalink
D plan change WRONGC
riyaz145
Tue, 02/26/2013 - 12:29
Permalink
6th question
Even though first I initially went for A, then chose option D as the last statement of option A says "within control limit"....
However, out of control means, the points have to exceed control limits, Isn't it ?
Do comment. Thanks
sunitaPMP
Sat, 03/09/2013 - 18:40
Permalink
Hello Pawar Ji,For last
Hello Pawar Ji,
For last question regarding Control limit why Option B) is not correct?
ritusri
Thu, 02/28/2013 - 04:43
Permalink
Winthin control limit but if
Winthin control limit but if seven consecutive point either side of the mean then project is out of control, this is called as rule of seven.
happyinlove505
Thu, 02/28/2013 - 04:57
Permalink
I think the 111 question is
I think the 111 question is wrong.
It specifies EV and AC and CPI which is not equal to EV/AC.
I think either the question is not correct, or that is why we have "none of the above" answer.
Anyway, can somebody advise if it is possible for CPI to be not equal to EV/AC like in the case above?
sandeep12
Fri, 03/01/2013 - 06:42
Permalink
PMP mock questions
For first question the answer is A) Mitigate. It is given in page 304 PMBOK. Rest all are correct based on sspawar answers.
sunitaPMP
Sat, 03/09/2013 - 18:35
Permalink
Hi Sandeep?For First
Hi Sandeep?
For First question,Is it A?
I would go with option D.
sunitaPMP
Sat, 03/09/2013 - 18:36
Permalink
Hi Amber,What is the correct
Hi Amber,
What is the correct ans for First question?
sunitaPMP
Sat, 03/09/2013 - 18:38
Permalink
Hi Amber,also let us know teh
Hi Amber,
also let us know teh correct ans for last question regarding control limit.
ashshe24
Sun, 03/10/2013 - 13:01
Permalink
I bilieve the answer is
I bilieve the answer is Mitigate
Jeff Harvey
Mon, 03/11/2013 - 11:32
Permalink
Good questions. You can also
Good questions. You can also get very good PMP mock questions from various other resources available over internet. Right from being available with different training providers like PMstudy, Simplilearn, etc to various other sources.
Jeff