Q on Critical Path
Submitted by peeyushm on Tue, 02/05/2013 - 12:37
Please share schedule network diagram for following to get critical path
In the project network diagram shown below, which of the following tasks will have some float?

1) A
2) E
3) F
4) C
Forums:


peeyushm
Tue, 02/05/2013 - 12:47
Permalink
Not able to paste image from
Not able to paste image from word.
sspawar
Tue, 02/05/2013 - 14:03
Permalink
No problem you can write
No problem
you can write down all activities with their durations and series of paths
for example
Activity Dur
A 2
B 5
C 6
D 8
E 5
Now paths like
A-C-D -E
B-C-E
On this basis a network diagram can be sketched and can be answered.
There any relation like FS/FF/SS OR LEAD/LAG canbe mentioned.
peeyushm
Wed, 02/06/2013 - 05:56
Permalink
Here are paths and their
Here are paths and their durations:
Path Duration
A-B --->3
A-E ---> 2
B-C ---> 4
C-D ---> 3
D-H ---> 3
E-C ---> 5
E-F ---> 4
F-G ---> 4
C-G ---> 2
G-H ---> 4
sspawar
Wed, 02/06/2013 - 09:46
Permalink
3
B
4
C
3
D
3
H
A
5
2
E
F
G
2
4
4
4
PATH
AEFGH = 14
All other path have 13 days
hence activitIES on critical path=
AEFGH
HENCE OPTION D IS ANSWER
sspawar
Wed, 02/06/2013 - 11:32
Permalink
Above presentation is
Above presentation is example of AOA method.
Here option are given like - A E F C are not activities, but this are nodes.
hence figure only as above.
In this method drawbacks is that - forward and backward passes can not be indicated.
Hence AON is better than this. In PMP generally this AON method is asked, like in case of ES/ EF/LS/LF.
Above example can be solved by AON like this:
1
3
4
7
8
10
11
13
AB/3
BC/4
CD/3
DH/3
2
4
5
8
9
11
12
14
START
END
1
2
3
7
8
9
AE/2
EC/5
CG/2
1
2
4
8
9
10
3
6
7
10
11
14
EF/4
FG/4
GH/4
3
6
7
10
11
14
peeyushm
Wed, 02/06/2013 - 12:21
Permalink
Thank You Sir. I was mainly
Thank You Sir. I was mainly having problem to convert these paths to activites and to get the end. Now i got it.