A question from Oliver's Sample test
Hi Can someone please let me know the reason behind the answer in the below Question..
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8
and an SPI of 1.25. What is a plausible explanation for that?
1. The project was terminated early. At that time, it was over budget and ahead
of schedule.
2. The project has produced additional deliverables which were originally not
required.
3. The project has evidently been finished under budget and behind of schedule.
4. The project has evidently been finished over budget and ahead of schedule.
Answer is 1.
Where is the indication in the question that project was terminated early?
Thanks,
Vani


raza82
Wed, 01/30/2013 - 07:48
Permalink
Brief Explaination
At the end of project SPI =EV/PV = 1 if the project is closed
and at the end of project SPI wont be 1 only in the case where project is terminated.
So we can figure out that the project was terminated
Anyways u can find some discussion here for this topic
http://pmp.groupsite.com/beta/discussion/topics/303089/messages
nvkvani
Wed, 01/30/2013 - 09:35
Permalink
Thanks
Thanks that clarified the doubt.
sspawar
Thu, 01/31/2013 - 01:55
Permalink
SPI = 1.25 it means work was
SPI = 1.25 it means work was in running condition and was closed. hence terminated.
SPI = 1 when EAC , and BASELINE is updated at completion