Is the answer correct ??

A Project Coordinator may typically be found in what type of organization?

A. Strong Matrix

B. Weak Matric

C. Projectized

D. Functional

 

The correct answer provided is "C". Is this correct. I thought it would be "Weak Matrix".

C is definitely wrong answer. I would go for Weak Matrix.

Similar topic can be found here: http://pmzilla.com/project-coordinator-may-typically-be-found-what-type-...

BTW, if the same question would be asked about Project Expediter, what would be the right answer? I believe, it would be Functional. Please correct me if I am wrong.


 


Kim heldman


============


 Functional managers who have a lot of authority and power working with project coordinators


who have minimal authority and power characterizes a weak matrix organization.


Project managers in weak matrix organizations are sometimes called



project coordinators,

project leaders

, or project expeditors. For more information, please see Chapter 1.

functional organization will be headed by pure (100 %)  functional manager.


projectized organization will be headed by pure (100%) project manager


strong matrix organization will be headed by almost by PM , not reporting to FM.


weak metrix organization  will have co-ordinator or expideter.


hence B will be the answer.

As per my understanding and research both Project Coordinator & Expeditor are in Weak Matrix organization type. 

Project Expediators are most likely found in Functional Organizations. Although sometimes in Weak Matrix as well, but called as Coordinators who report to a little higher level.

What difference would it make if the question were rephrased as:

A Project manager is MOST LIKELY to act as a Project coordinator in which of the following organizations?

A: Strong matrix

B: Weak matrix

C: Projectized

D: Functional

I guess it still remains Weak Matrix.

I am for WM

 Weak Matrix: In weak matrix, the project manager has a part time role with very limited power and authority. His role will be more like a coordinator or an expediter. Weak matrix structure is very close to the functional organization structure. In weak matrix structure, the functional manager controls the project budget.