Is the answer correct ??
Submitted by phani112 on Thu, 01/24/2013 - 05:30
A Project Coordinator may typically be found in what type of organization?
A. Strong Matrix
B. Weak Matric
C. Projectized
D. Functional
The correct answer provided is "C". Is this correct. I thought it would be "Weak Matrix".
Forums:


happyinlove505
Thu, 01/24/2013 - 05:45
Permalink
C is definitely wrong answer.
C is definitely wrong answer. I would go for Weak Matrix.
Similar topic can be found here: http://pmzilla.com/project-coordinator-may-typically-be-found-what-type-...
BTW, if the same question would be asked about Project Expediter, what would be the right answer? I believe, it would be Functional. Please correct me if I am wrong.
anand2381
Thu, 01/24/2013 - 05:56
Permalink
Weak Matrix will have Project co-ordinator
Kim heldman
============
Functional managers who have a lot of authority and power working with project coordinators
who have minimal authority and power characterizes a weak matrix organization.
Project managers in weak matrix organizations are sometimes called
project coordinators,
project leaders
, or project expeditors. For more information, please see Chapter 1.sspawar
Thu, 01/24/2013 - 06:00
Permalink
functional will be headed by
functional organization will be headed by pure (100 %) functional manager.
projectized organization will be headed by pure (100%) project manager
strong matrix organization will be headed by almost by PM , not reporting to FM.
weak metrix organization will have co-ordinator or expideter.
hence B will be the answer.
phani112
Fri, 01/25/2013 - 05:14
Permalink
As per my understanding and
As per my understanding and research both Project Coordinator & Expeditor are in Weak Matrix organization type.
rjbuzzing
Sat, 01/26/2013 - 17:03
Permalink
Project Expediators are most
Project Expediators are most likely found in Functional Organizations. Although sometimes in Weak Matrix as well, but called as Coordinators who report to a little higher level.
steelproject2012
Sat, 01/26/2013 - 15:27
Permalink
What difference would it make
What difference would it make if the question were rephrased as:
A Project manager is MOST LIKELY to act as a Project coordinator in which of the following organizations?
A: Strong matrix
B: Weak matrix
C: Projectized
D: Functional
rjbuzzing
Sat, 01/26/2013 - 17:02
Permalink
I guess it still remains Weak
I guess it still remains Weak Matrix.
madunix (not verified)
Tue, 01/29/2013 - 11:47
Permalink
I am for WM Weak Matrix: In
I am for WM
Weak Matrix: In weak matrix, the project manager has a part time role with very limited power and authority. His role will be more like a coordinator or an expediter. Weak matrix structure is very close to the functional organization structure. In weak matrix structure, the functional manager controls the project budget.