Question

I am a new project manager joined a on going project. I would like to see the definition of project and work which needs to be performed for the project. Which is the Best place to see that?


Project Plan


Project Scope Statement


WBS


 


 

Project Scope Statement (PSS) constitutes what needs to be done on the project for its completion. PSS holds the answer RD...


 


Warmly, KK....

If you want to see the definition then SOW is the best place to see that.


not in options


from options for on going project - PSS -more descriptive


WBS and Project plan - no

Thanks both of you.  Right answer is PS.


But, I was thinking why he can not look into PM Plan with all the baselines and variances to look into the progress of project and how much  work is left. PS is also part of PM Plan.