What should you do first?
Submitted by Jp2786 on Tue, 05/27/2014 - 03:26
1. Your manager gives you a project charter and asks you to begin work immediately and to provide her with a schedule. What should you do first?
a) Begin estimating the activities necessary to complete the scope of work.
b) Begin creating a Project Scope Statement.
c) Create an activity list and then begin to assign the activities to resources.
d) Identify a team and obtain approval for their participation from their functional
Please let us know why u chose that particular answer choice?
Forums:


admin
Tue, 05/27/2014 - 03:49
Permalink
First you need a team of
First you need a team of people to work on, then you should know the project scope, once you know the scope you can details out activities and resources required. Then you assign resources and all this will finally result into a project schedule.
Sundara.damaraj...
Tue, 05/27/2014 - 05:14
Permalink
What should you do first?
It is "B" is part of Define scope
A is part of create wbs
C is part of Define activities and others
D is part of Develop team.
A,C and D comes after B.
kumarks984
Tue, 05/27/2014 - 05:17
Permalink
Planning Team First
Answer should be "D"
Best Reference: Rita's Chart :)
Have the planning process by heart
sunku65
Tue, 05/27/2014 - 14:58
Permalink
Three choices A, B and C done
Three choices A, B and C done by with the Team not PM alone.
The answer is D.
Jp2786
Tue, 05/27/2014 - 18:07
Permalink
Even as per Rita chart B comes before D
Jp2786
Tue, 05/27/2014 - 18:11
Permalink
Even as per Rita chart B comes before D
Even as per Rita chart B comes before D, isnt it?
chullan88
Wed, 05/28/2014 - 07:13
Permalink
Hi,The answer is "D"The
Hi,
The answer is "D"
The answer can be reached through elimination process as well:
Project Scope Statement - We have not collected the requirements yet
Activity List and estimates - not possible unless you have WBS
If you are referring to Rita's book also,she clearly mentions Acquire project team should be read as Acquire final project team.Acuiring the inital team occurs early in planning stage.
Could you please mention the source of the question?
Sundara.damaraj...
Wed, 05/28/2014 - 10:34
Permalink
Hi,The answer is "D"The
Dear Chullan88,
You said that, did not collect requirements.. Then how can you conclude answer "D". (Identifying team from functional Mgr).
Are you saying initial team can be acquired without "Collect requirements" and Create Scope?
Sandy10001
Wed, 10/08/2014 - 16:42
Permalink
Scope
b) Begin creating a Project Scope Statement.
You can't do the others until you know the scope of the project.