Which of the following are ALL tools and techniques of the Manage Project Team
process?
a) Watch the team; report on team member’s performance and issue conflict resolutions.
b) Use appropriate conflict resolution techniques, do a 360 degree feedback assessment, and update the project management plan
c) do a 360 degree feedback assessment, verify critical resource availability, and watch the team
d) report on team member’s performance, Use appropriate conflict resolution techniques, do a 360 degree feedback assessment.
I'm not sure how to go about elimiating the choices can some one help pls.
Thanks in advance
Regards
Jp
Forums:


admin
Fri, 04/11/2014 - 10:35
Permalink
Updating PM plan is not Tool
Updating PM plan is not Tool / Technique, so should be B.
Jp2786
Fri, 04/11/2014 - 16:59
Permalink
Confused.
Hey...Thanks for your response.
I guess there is a typo in your reponse. If its Updating PM plan not a Tool/Technique then how can it be B?
Please clarify.
Reagrds
Jp
admin
Fri, 04/11/2014 - 17:03
Permalink
Check the PMBoK , i think its
Check the PMBoK , i think its straightforward, Answer is A.
Jp2786
Fri, 04/11/2014 - 17:19
Permalink
Yes How did you eliminate C
hey.... Thanks for your response.
Yes How did you eliminate C. I mean isn't verify critical resource availability and do a 360 degree feedback assessment also done as a part of Manage project team
Cheers
Jp
Latunde
Sat, 04/12/2014 - 20:54
Permalink
Why not D?
Why not D?
Jp2786
Sat, 04/12/2014 - 21:20
Permalink
Not sure but guessing
Here is what PMBOK says as Tools and Techniques
a. Observation and converstaion
b Project Performance Appraisal
c. Conflict Management
d. Interpersonal skills.
Answer choice A and D are below
a) Watch the team; report on team member’s performance and issue conflict resolutions.
d) report on team member’s performance, Use appropriate conflict resolution techniques, do a 360 degree feedback assessment.
A matches the T&T better than D moreover do a "360 degree feedback assessment is a step" in " report on team member’s performance" . I dont think its TT by itself.
let me know if you have a different view point.
Cheers
Jp
mattR
Wed, 04/16/2014 - 03:57
Permalink
360 degree feedback is not listed as a tool
360 is not listed as a tool. 360 is a general personnel evaluation technique, not a Manage Project Team tool. Project Management Plan Update is an output, not an input.
I agree it's A.
sunku65
Sun, 04/20/2014 - 09:26
Permalink
Correst answer is A.Watch the
Correst answer is A.
Watch the Team -----> comes under Observation and conversation tool