Need Help HR question.

Which of the following are ALL tools and techniques of the Manage Project Team
process?
a) Watch the team; report on team member’s performance and issue conflict resolutions.
b) Use appropriate conflict resolution techniques, do a 360 degree feedback assessment, and update the project management plan
c) do a 360 degree feedback assessment, verify critical resource availability, and watch the team
d) report on team member’s performance, Use appropriate conflict resolution techniques, do a 360 degree feedback assessment. 
 
I'm not sure how to go about elimiating the choices can some one help pls. 
 
Thanks in advance
 
Regards
Jp
admin's picture

Updating PM plan is not Tool / Technique, so should be B.

Hey...Thanks for your response.

I guess there is a typo in your reponse. If its Updating PM plan not a Tool/Technique then how can it be B?

Please clarify.

Reagrds

Jp

admin's picture

Check the PMBoK , i think its straightforward, Answer is A.

hey.... Thanks for your response.

Yes How did you eliminate C. I mean isn't  verify critical resource availability and do a 360 degree feedback assessment also done as a part of Manage project team 

Cheers

Jp

Why not D?

Here is what PMBOK says as Tools and Techniques

a. Observation and converstaion

b Project Performance Appraisal

c. Conflict Management

d. Interpersonal skills.

Answer choice A and D are below

a) Watch the team; report on team member’s performance and issue conflict resolutions.

d) report on team member’s performance, Use appropriate conflict resolution techniques, do a 360 degree feedback assessment. 

A matches the T&T better than D moreover do a "360 degree feedback assessment is a step" in " report on team member’s performance" . I dont think its TT by itself. 

let me know if you have a different view point.

Cheers

Jp

360 is not listed as a tool.  360 is a general personnel evaluation technique, not a Manage Project Team tool.  Project Management Plan Update is an output, not an input. 

I agree it's A.  

Correst answer is A.

Watch the Team -----> comes under Observation and conversation tool

Team members performance ---> comes under Project performance tool
 
issue conflict resolution  ----------> comes under conflict management tool
 
 
Whereas  PM Plan update and 360 degree is not a tool in Manage TProject Team