is customer approval required on Project charter?
ginumon
Thu, 07/18/2013 - 13:46
Permalink
In Some cases the customer can be the sponsor , and hence customer can sign/approve the charter I believe. In normal case if the sponsor is internal , you don't need an approval from the customer on the charter.
Please correct me if I am wrong.
cnppmp1
Thu, 07/18/2013 - 14:37
For external customer you are working as project manager you ensure you have project charter signed by customer.
For internal project, then Sponsor would sign the project charter.
Regards
CN Patil
ma498
Thu, 07/18/2013 - 16:40
Hi,
Thanks, now point is clear, to understand internal/external requirement
VBR, Emma
ginumon
Thu, 07/18/2013 - 13:46
Permalink
My two cents
In Some cases the customer can be the sponsor , and hence customer can sign/approve the charter I believe. In normal case if the sponsor is internal , you don't need an approval from the customer on the charter.
Please correct me if I am wrong.
cnppmp1
Thu, 07/18/2013 - 14:37
Permalink
Yes
For external customer you are working as project manager you ensure you have project charter signed by customer.
For internal project, then Sponsor would sign the project charter.
Regards
CN Patil
ma498
Thu, 07/18/2013 - 16:40
Permalink
Thanks PC approval
Hi,
Thanks, now point is clear, to understand internal/external requirement
VBR, Emma